9.

If internal finishing and painting can be started simultaneously at the end of construction, then what is the overflow of the project as a percentage of the estimated total time of completion of the project ?

PGREF-717
A: 27.27%
B: 33.33%
C: 42.85%
D: Cannot be determined

The answer is: C