MBA CDOE (USOL) Panjab University MBA Entrance Exam with MCQ Answers 2014

Practice Mode:
33.

Ram and Sham can do a work in 6 and 12 days respectively. Ram starts the work and Sham joins after 3 days to finish the work together. For how many days Sham worked?

A: 6 days
B: 5 days
C: 2 days
D: None of these

The answer is: C