PU-MET : Panjab University MBA Entrance Exam with MCQ Answers 2022

Practice Mode:
56.

If the toll is to be collected through an outsourced agency by allowing a maximum 10% commission, how much amount should be permitted to be collected by the outsourced agency, so that the project is supported with Rs. 4910 crores?

PGREF-707
A: Rs 6213 crores
B: Rs 5827 crores
C: Rs 5401 crores
D: Rs 5316 crores

The answer is: C